Mahat’s claim of 600 MW addition this year unachievable
Bhrikuti Rai / August 24, 2015
Annex 18 of the budget for the fiscal year 2015/2016 unveiled by Finance Minister Ram Sharan Mahat states that the country’s power generation will increase by 600 MW in this fiscal year raising the installed capacity to 1498 MW.
Meeting this target is impossible unless the hydropower projects that are near completion come into operation within this fiscal year. The following are some of those projects nearing completion and their current status:
Project | Capacity | Scheduled completion date | Present status |
Chameliya | 30 MW | 2014/15 | Minimal damage by the earthquakes. Expected to complete within this fiscal year. |
Kulekhani 3 | 14 MW | 2014/15 | Minimal damage by the earthquakes. Expected to complete within this fiscal year. |
Upper Trishuli 3A | 60 MW | 2015/16 | Unable start work on site since the earthquakes. |
Upper Modi A | 42 MW | 2015/16 | Minimal damage by the earthquakes. Expected to complete within this fiscal year. |
Upper Tamakoshi | 456 MW | 2016/17 | Unable to start work on site since the earthquakes. |
Source: Annual Progress Report by Ministry of Energy, page 43 and 45; officials of the projects concerned.
Chameliya and Kulekhani-3, which had missed the scheduled completion deadlines earlier, have been expected to come into operation within this fiscal year, according to this year’s budget. Although Upper Tamakoshi’s completion was scheduled after 2016, the budget has expected the project to be complete early — within this fiscal year. Based on these slated completion dates the budget included the 600 MW to be added to the national grid.
However, many of these projects were damaged by the earthquake on 25 April and strong aftershocks that jolted the country. In order to assess the post-earthquake condition of the hydro power projects we talked to officials at the Ministry of Energy and the under construction projects.
Bigyan Prasad Shrestha, head of the Upper Tamakoshi projects says, “Landslides have triggered rock falls on the roads connecting the project site, we think this might push back the project’s completion date by another year.”
Gokarna Pantha of the Department for Electricity Development also says that the damage caused by the earthquakes will make it difficult for some of the under construction projects to see completion within 2015/16. “The 600 MW mentioned in the budget could have been added to the national grid had there been no earthquakes, but now the target seems a bit unrealistic because of the damage caused,” says Pantha.
The Post Disaster Needs Assessment (PDNA) prepared in June estimates Nepal’s energy sector sustained total loss and damage close to US$ 18 million. It states that several hydropower facilities generating about 115 MW have been severely damaged and facilities with total capacity of 60 MW have suffered partial damage. The country’s total installed capacity of hydropower projects this year has reached 787 MW.
Wrong numbers
When we talked to Pantha of the Department of Electricity Development to inquire about the numerical mismatch we learnt that the prediction of the Ministry of Finance about 600 MW addition was based on the figures worked out before the earthquake.
Therefore, the numbers (based on the pre- earthquake scenario) presented in the budget almost two and half months after the earthquake ended up turn out to be incorrect.
This material is copyrighted but may be used for any purpose by giving due credit to southasiacheck.org.
Comments
Latest Stories
- In Public Interest Covid-19 cases are low, but that’s not an excuse to avoid vaccination
- In Public Interest What is BF.7, the sub-variant that has the world by its grip?
- In Public Interest Threat of a new Covid-19 wave looms large amid vaccine shortage in Nepal
- In Public Interest As cases decline, Covid-19 test centres in Kathmandu are desolate lot
- In Public Interest Dengue test fee disparity has patients wondering if they’re being cheated
- In Public Interest As dengue rages on, confusion galore about what it is and what its symptoms are. Here’s what you need to know
In Public Interest
Covid-19 cases are low, but that’s not an excuse to avoid vaccination The Pfizer-BioNTech bivalent vaccines authorised by the Nepal Government provide better protection a... Read More- What is BF.7, the sub-variant that has the world by its grip?
- Threat of a new Covid-19 wave looms large amid vaccine shortage in Nepal
- As cases decline, Covid-19 test centres in Kathmandu are desolate lot
- Dengue test fee disparity has patients wondering if they’re being cheated
- As dengue rages on, confusion galore about what it is and what its symptoms are. Here’s what you need to know